  • This portlet displays the monthly allocation per resource. The PM can view by the RM or the resource to get the data for monthly resource allocations. The table below describes the available filter fields in the portlet.
    Column Label Description
    Work Effort Manager Manager of the Investment the Work Effort is on
    Work Effort Active Active status of the Investment the Work Effort is on
    Resource Resource’s Name
    Internal Resource ID Resource’s ID
    Zero Allocation Show Allocations that equal zero
    Open for Time Entry Is the Resource Open for Time Entry
    Resource Active Resource’s Active status
    Role Resource’s Primary Role
    OBS Unit Resource’s OBS
    Start Allocation Start Time to filter by
    End Allocation Finish time to filter by
       
  • This Portlet produces a Grid View of Resources using total Resource Allocation from each Project’s Team / Staff, per month; output is expressed as a %.  Users can specify which Resource OBS to use as a Filter (unit and descendants is assumed) as well as a Start/End Date.
  • This Portlet produces a Stacked Chart of Projects using total Resource Allocation from each Project’s Team / Staff, per month.  Users can specify which Resource OBS to use as a Filter (unit and descendants is assumed) as well as a Start/End Date Range.
  • This portlet displays a Pie Chart of a Portfolio’s Realized Benefits partitioned into pie slices by the portfolio’s Investments’ Objectives. Clicking on any pie slice (Objective) drills-down into a portlet that lists the Investments that make up that slice.
  • Bar Chart displays average percent variance for all active projects by OBS unit.  Percent variance = Planned Cost - Budgeted Cost / Budgeted Cost * 100.  Projects with no Budgeted Cost are ignored for the calculation.  Then all project variance percentages are algebraically added (some may be negative), and divided by total projects with a variance.  This yields the Average Percent Variance.  This calculation is performed for active projects in each OBS unit.  OBS units include all units at all levels where projects are attached.  Portlet filterable by OBS, Financial Status, and Financially Approved.  Vertical axis = OBS Unit Name.  Horizontal axis = Variance Percent.  Data value = Average Percent Variance.  Mouseover value = OBS Name + Average Variance Percent.
  • The Milestone Task Dependency portlet shows the milestone task dependency count and has a drilldown to the details. The portlet looks at the dependency impact on milestones, and is not limited to just dependencies that are on different projects. The lag days calculation is based off of the maximum dependency impact and the drilldown portlet (Milestone Task Dependency Details :::: rego_milestone_dependency_det)shows the details for each.
  • Resource Availability – 4 Weeks is a grid portlet that displays all resources with their total allocated hours by week, and an average availability percent (4 Wk Avail %) for next four weeks.  If % Available is negative, this indicates an over-allocation.  Zero% Average Availability indicates fully allocated (no remaining availability). Filterable by Role, Resource, Resource Type, Full-Time/Part-Time, Availability Range.  Contractor Type is a custom attribute (Lookup - String) created on the Resource object. It is attached to the lookup, Contractor Type (Lookup ID: REGO_CONTRACTOR_TYPE) that has static values Part Time (PT) and Full Time(FT).
  • This portlet will allow administrators or other managers to see what resources have been granted instance rights to any investment. Filtering is available by resource, investment or right.
  • Grid Portlet displays project and task data--including name, dates, status, effort, %Complete, and schedule.  Portlet initially displays project data.  But there is a + sign toggle, which, when clicked, reveals task data, and the toggle becomes a – sign.  User can choose to Automatically Expand all levels from Options Icon>Configure>List Column Section>Options.  Portlet supports up to 10 levels of WBS.  Portlet filterable by project name and ID, OBS structure, manager name, active/inactive, and open for time entry.
  • This portlet depicts the Resource Utilization by comparing actual hours booked as a percentage of total resource availability grouped and totaled by OBS Unit in a hierarchical fashion.  Resource availability is determined by the working days and daily availability on the individual Resource Calendar and is depicted on a Monthly basis.  This portlet uses Monthly Times and the Time Slice job may need to run before the end user will see results in the portlet.   The portlet filters for Project Activity, Resource Open for Time, Resource Activity, and Employment time have been added to OBS Type and the Start and Finish dates.  The OBS summary totals show on a single line, but can be clicked (+) to roll out the details behind each OBS total.
  • This portlet displays the projects by Stage in a pie chart. Every piece of the pie chart represents a stage of the Project Management methodology applied. The portlet also shows the number of projects on each stage. The legend displays all the different project stages appearing on the portlet. This portlet can be filtered to show only projects from a particular OBS unit or for a particular Project Manager.
  • The portlet - Attributes on Portlets - details all attributes on every portlet in the system, whether the person viewing the list has rights to the returned portlets. The table below describes the available columns in the portlet.
    Column Label Description
    Portlet Name Name of the portlet
    Portlet Code ID of the portlet
    Field Name Name of the attribute
    Field Code ID of the attribute
    Virtual Is the attribute virtual or not
    id Internal code used by the query
Go to Top